Q: Allowance for contingencies can be expressed as a percentage of _______.
A.
total cost
B.
supervision charges
C.
establishment charges
D.
rate of each item
Correct Answer:
Option A - Contingencies (3-5% of project Cost)–
It is unforeseen/incidental expenses which cannot be predicted prior to the execution of project. Example–severe accident, specialist visit on site, etc.
A. Contingencies (3-5% of project Cost)–
It is unforeseen/incidental expenses which cannot be predicted prior to the execution of project. Example–severe accident, specialist visit on site, etc.
Explanations:
Contingencies (3-5% of project Cost)–
It is unforeseen/incidental expenses which cannot be predicted prior to the execution of project. Example–severe accident, specialist visit on site, etc.
Download Our App
Download our app to know more Lorem ipsum dolor sit amet consectetur adipisicing elit.
Excepturi, esse.
YOU ARE NOT LOGIN
Unlocking possibilities: Login required for a world of personalized
experiences.