Explanations:
Estimation of air content–Approximate amount of entrapped air to be expected in normal (non air-entrained) concrete is given as per IS 10262-2019. Table 3– Nominal maximum size Entrapped air, as % of of aggregate (mm) volume of concrete 10 1.5 20 1.0 40 0.8